星期五, 5 12 月, 2025
Home PV Technology Solar Operations’ myPV ClearSky units help Pine Gate project satisfy interconnection requirements

Solar Operations’ myPV ClearSky units help Pine Gate project satisfy interconnection requirements

Last month, Pine Gate Renewable’s Grissom Solar project went commercial. Grissom is a 6.9-MW solar + 10-MWh battery storage site. Pine Gate requested support from Solar Operations Solutions (Solar-Ops) to overcome the challenging requirements that surfaced during the utility’s interconnection study.

The Grissom project has a single 5-MW interconnection that must be maintained when solar and battery storage are working under the supervision of a third-party SCADA system. Both the solar inverters and the battery storage system are independently AC-coupled to the interconnection through two myPV ClearSky units from Solar-Ops.

Each ClearSky provides revenue-grade metering and recloser protection while eliminating much of the overhead medium-voltage equipment, reducing construction time and long-term operational costs.

“AC coupling battery storage to new or existing solar facilities is increasingly common as developers and owner operators look to maximize value from their existing interconnection agreements and PPAs,” said Brad Micallef, Solar-Ops’ president. “The ClearSky product line is ideal for these applications due to its small size and built-in ability to satisfy protection and reporting requirements from the utility and ITC.”

Utilities have concerns regarding power quality issues from increased inrush current. Therefore, distribution interconnected generators like Grissom can face approval challenges. When AC-coupled battery storage is added to a solar facility, the additional transformers increase the chances of inrush current being a problem.

A distribution grid will experience a rapid reduction in voltage because of the sudden demand for current when too many transformers are energized at the same time. This sudden rapid voltage change can lead to equipment damage for power customers and requires mitigation for the utility to operate within IEEE standards.

Normally requiring a dedicated piece of equipment, the Grissom facility was able to mitigate its inrush current by sequencing the two myPV ClearSky units’ internal medium voltage reclosers. Programming one ClearSky to energize upon grid restoration and the other to delay energization by a few seconds, the inrush event was reduced to an acceptable level.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Australia solar Installation hits 40 GW

An IEA survey of solar power applications in Australia shows that the country installed 5.2 GW of solar capacity in 2024 and reached a...

Versiris Energy completes logistically tricky rooftop solar project

Versiris Energy completed a 575.36-kWDC rooftop solar project for a national commercial retail facility in Chanhassen, Minnesota. Versisis, a commercial solar developer and subsidiary...

Recurrent Energy Sells 275 MW Solar-Plus-Storage Project in New South Wales to European Investor

Recurrent Energy, a subsidiary of Canadian Solar Inc. and a global developer of solar and energy storage assets, has finalized the sale of its...

Azerbaijan seeks Chinese help in achieving “green” power dream

Azerbaijan is hoping China can play a big role in helping Baku fulfill its ambitions of building a “green energy corridor” to Europe. Azerbaijani officials...