Home PV News Vestas receives 59 MW wind turbine order

Vestas receives 59 MW wind turbine order

Vestas has received a 59 MW order from Exelon Wind for 33 V100-1.8 MW turbines for the Harvest II Wind Project in Michigan.


Vestas will deliver, commission and maintain the turbines for 10 years as part of the contract. All of the wind turbine components will be built at Vestas' manufacturing facilities in Colorado.


Delivery is scheduled for mid-2012, with commissioning scheduled for late 2012.


The Harvest I Wind Project was commissioned in 2008 and uses 32 Vestas V82-1.65 MW turbines.


Exelon Wind also owns the Michigan Wind 2 Project, which is under construction and will include 50 V100-1.8 MW turbines. Michigan Wind 2 is expected to be completed by the end of 2011.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Australia solar Installation hits 40 GW

An IEA survey of solar power applications in Australia shows that the country installed 5.2 GW of solar capacity in 2024 and reached a...

Versiris Energy completes logistically tricky rooftop solar project

Versiris Energy completed a 575.36-kWDC rooftop solar project for a national commercial retail facility in Chanhassen, Minnesota. Versisis, a commercial solar developer and subsidiary...

Recurrent Energy Sells 275 MW Solar-Plus-Storage Project in New South Wales to European Investor

Recurrent Energy, a subsidiary of Canadian Solar Inc. and a global developer of solar and energy storage assets, has finalized the sale of its...

Azerbaijan seeks Chinese help in achieving “green” power dream

Azerbaijan is hoping China can play a big role in helping Baku fulfill its ambitions of building a “green energy corridor” to Europe. Azerbaijani officials...