Fire Island wind power project moves closer to reality


A deal that would allow Cook Inlet Region Inc. to build an electricity-generating wind turbine farm on Fire Island is in the final stages.


The board of Chugach Electric Association, the biggest power utility in Alaska, is scheduled to consider today a proposed contract to buy wind power from CIRI.


"I don't see any problem," Chugach board member Jim Nordlund said Tuesday. The board last week unanimously agreed to terms that make up the deal, he said.


The agreement calls for CIRI to deliver electricity from 11 wind turbines capable of producing a maximum of 17.6 megawatts of power — about enough to provide electricity to 6,000 households, said Jim Jager, spokesman for CIRI.


The nest of turbines would sit on the southern end of Fire Island, and visible from parts of the Anchorage coast, such as in Kincaid Park. Each turbine would rise some 260 feet with 130-foot blades, according to information on CIRI's web site. The Atwood state office building downtown is just over 260 feet tall.


The 11-turbine wind farm is one-third of the size that CIRI hopes to build eventually.



But at this point, Chugach is the only utility to sign on to buy Fire Island power, so CIRI created a scaled-back the first phase, Jager said.


The city-owned Municipal Light and Power made an offer to CIRI earlier this year, but CIRI executives said it was so low that it was unworkable.


The Anchorage Assembly passed a resolution in favor of the city getting in on the project, and created a committee to look into it. But Assemblyman Ernie Hall said the committee hasn't met yet because when he contacted CIRI officials, they asked him to wait until Chugach negotiations were completed.


Chugach serves about 80,000 homes and businesses in Southcentral Alaska directly, including Anchorage residents south of Tudor Road or East of Boniface Parkway. It also sells power to other utilities.


ML&P has 30,000 customers.


The price Chugach and CIRI agreed to for wind-generated electricity is $97 per megawatt hour.


That's higher than the average cost of power now, said Jager, but, "This is 25 years at a fixed price. As energy prices go up it will look more and more attractive."


Chugach expects electric rates for its customers to rise slightly in the short-term, by about $20 per year for an average household that uses 700 kilowatt hours of electricity per month, said Nordlund.


The wind farm will provide about 4 percent of Chugach's power.


It's a modest amount, but a significant move, said Chris Rose, executive director of the Renewable Energy Alaska Project. "Now we'll be able to see the benefits of wind power close to home."


Using renewable energy like wind power that doesn't have fuel costs is a way to lessen the blow when natural gas prices rise, Rose said.


There's a looming shortage of Cook Inlet gas.


"The natural gas prices utilities are paying right now will go up after current contracts expire," Rose said.


While Chugach and CIRI executives have reached agreement, there are more steps before the wind project becomes reality.


Here's what happens next:


• The Chugach board meets at 3 p.m. Wednesday to consider the contract.


• The CIRI board meets Monday to do the same, said Jager.


• The Regulatory Commission of Alaska also has to OK the deal.


CIRI will ask for expedited approval by Sept. 15, so the company can do enough construction work this fall to qualify for a federal stimulus grant, said Jager.


CIRI doesn't know how much federal money it will be eligible for. But that money will go directly to pay for construction costs, he said.


The company does not yet have a cost estimate for the 11-turbine project, he said.


It would have cost $162.2 million to build the project as CIRI initially proposed it, with 33 turbines, he said.


In addition to the federal money, a state grant of $25 million is available to build the underwater transmission line to get electricity from Fire Island to Anchorage.


CIRI would build the transmission line, then Chugach would be responsible for operating and maintaining the line.


CIRI's goal is to build the 11 turbines and get the transmission cable laid between Fire Island and the mainland all by late 2012, said Jager.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

28.29%! LONGi’s crystalline silicon cell efficiency breaks world record again

9月24日(当地时间),隆基绿色能源在欧洲正式发布了一项重大技术突破:其自主研发的高低温复合钝化背接触(HIBC)电池的光电转换效率达到28.29%,并已获得德国哈默尔恩太阳能研究所(ISFH)的认证。 这是隆基今年第三次打破晶体硅电池效率的世界纪录,此前已分别达到28.04%、28.13%和28.29%。最新的效率数据接近理论极限,达到最大值的96.2%。HIBC 电池的问世是隆基“广涉、聚焦”研发战略的里程碑式成果。通过整合多种主流电池技术的优势,公司实现了涵盖电池结构设计、核心材料制备、生产工艺和理论效率建模等各个环节的全面系统创新。此次成功有力地展现了隆基对高效电池领域的坚定承诺、自主创新能力以及核心技术的精湛掌握。 与电池一同亮相的还有采用HIBC电池技术打造的功率超过700W的组件,标志着这项前沿技术成功实现量产。这也凸显了隆基在高端光伏产品制造和先进技术商业化方面的强大实力。 在全球能源转型的大背景下,隆基绿色能源始终致力于构建完整的清洁能源价值链,力求提供融合绿色电力、绿色氢能和储能的一体化解决方案。展望未来,隆基将继续坚持自主创新,通过技术革新推动行业发展。公司致力于为全球市场提供高品质、多功能的光伏产品,积极支持全球能源转型,并携手构建以零碳排放和可持续发展为特征的绿色能源新格局。

Croatia’s Zito launches 3.9 mln euro PV power plant

克罗地亚食品生产商Zito周三宣布,已在位于克罗地亚东部切平(Cepin)的食用油工厂建成一座耗资385万欧元(约合440万美元)的太阳能光伏电站,装机容量为3.5兆瓦时(MWh)。这是该公司在该工厂建设的第二座光伏电站。Zito 在一份新闻稿中表示,该电站还配备了一套功率输出为4.5兆瓦、容量为9兆瓦时的储能系统。 该项目由欧盟支持的复苏与韧性计划共同出资,旨在帮助企业向节能高效型经济转型。 该电站于8月下旬投入试运行。其预计年发电量为5500兆瓦时,而工厂的总用电量超过10130兆瓦时。所发电量将用于满足工厂自身用电需求,剩余电力将存储在储能系统中。 “我们投资新建了一座太阳能发电厂,以补充现有的发电厂,该发电厂已于2023年投入运营。这座新电厂规模更大,两座电厂合计将满足切平油厂超过60%的总用电量,”该厂首席执行官卡洛·杜达斯表示。 这项对新太阳能发电厂的投资是在公司去年首次公开募股(IPO)期间宣布的,当时该公司在萨格勒布证券交易所筹集了1.3亿欧元。 周三,Zito(股票代码:ZITO)股价上涨1.14%,收于17.80欧元。 (1美元=0.867欧元)

Enexus, LONGi to deploy 50 MWh of BESS across two projects in Romania

Romanian renewables developer Enexus will deploy 50 MWh of battery energy storage system (BESS) capacity in the southern town of Titu, Dambovita county, using...

Solar panel catches fire on roof of industrial building near Okolona

A large industrial facility in south Louisville caught fire on Wednesday. The fire was reported just before 3 p.m. Wednesday in the 8700 block of...