Covid-19 lockdown: MNRE relaxes commissioning time for solar projects

A blanket extension equivalent to the period of lockdown and additional 30 days for normalisation after the end of the lockdown is allowed for completion of solar projects.

Source:pv magazine

Post industry’s demand, the Ministry of New and Renewable Energy (MNRE) has granted an extension of renewable project completion time equivalent to the period of Covid-19 lockdown and additional 30 days for normalisation after the end of the lockdown.

This will be a blanket extension, meaning there will be no requirement of the case to case examination. There will be no need to ask for any evidence for an extension due to lockdown.

“Renewable Energy implementing agencies may grant an extension of time for RE projects, on account of lockdown due to Covid-19, equivalent to the period of lockdown and additional 30 days for normalisation after the end of such lockdown”—read the ministry notification.

The Ministry has also said that all renewable energy implementing agencies of the MNRE will treat lockdown due to Covid-19, as a Force Majeure.

The decision was taken after renewable energy developers represented to the Ministry asking for a general time extension on account of lockdown (due to Covid-19) and additional time required for normalization after such lockdown.

MNRE had, earlier on March 20, issued directions to Solar Energy Corporation of India (SECI), NTPC and renewable energy departments of States to treat delay on account of supply chain disruption due to the spread of coronavirus in China or any other country, as a Force Majeure. It said the agencies might grant a suitable time extension for projects based on evidence/documents produced by developers in support of their respective claims.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Australia solar Installation hits 40 GW

An IEA survey of solar power applications in Australia shows that the country installed 5.2 GW of solar capacity in 2024 and reached a...

Versiris Energy completes logistically tricky rooftop solar project

Versiris Energy completed a 575.36-kWDC rooftop solar project for a national commercial retail facility in Chanhassen, Minnesota. Versisis, a commercial solar developer and subsidiary...

Recurrent Energy Sells 275 MW Solar-Plus-Storage Project in New South Wales to European Investor

Recurrent Energy, a subsidiary of Canadian Solar Inc. and a global developer of solar and energy storage assets, has finalized the sale of its...

Azerbaijan seeks Chinese help in achieving “green” power dream

Azerbaijan is hoping China can play a big role in helping Baku fulfill its ambitions of building a “green energy corridor” to Europe. Azerbaijani officials...