NRC rejects quick restart at Virginia nuclear plant

Nuclear regulators shot down an ambitious five-week timeline proposed to restart Dominion's (D.N) two North Anna reactors in Virginia during a public meeting on Thursday to discuss the Aug. 23 earthquake that knocked the station offline.


The 1,806-megawatt station has remained shut since it automatically tripped last month after the unusually strong 5.8 magnitude earthquake struck roughly 12 miles (19 km) from the plant in Mineral, Virginia.


On Thursday, Dominion officials said Unit 1 could be "physically" ready to restart by Sept. 22.


Dominion also said Unit 2 — set to begin a refueling outage in late September — could be refueled and ready to restart by mid-October.


An official from the Nuclear Regulatory Commission, however, noted that the agency's special inspection team may be finishing work at the site around Sept. 22 and warned that more meetings will likely be needed between Dominion officials and the NRC to better understand the company's plan to restart the plant.


Dominion's top nuclear officers gave details of the quake's seismic impact at the site, of the minor damage found at the site and outlined a lengthy list of inspections, tests and reports they plan to complete to satisfy the NRC that the North Anna reactors are safe to return to service. [ID:nN1E7870JL]


No other schedules for the restart were offered or suggested by the company or the NRC staff during the three-hour meeting.


Dominion officials said it now appears the reactors shut when the earthquake caused a problem inside the cores at both units rather than from the loss of outside power to the plant as initially reported.


"It looks like the (fuel) rods were going into the core prior to the transformer opening," possibly from a relay problem, a Dominion executive said.


Dominion is still working to understand the "root cause" of the plant shutdown as multiple automatic trip signals from various indicators were received within seconds of the quake.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Al Kharsaah: A Pioneering Solar Power Plant in Qatar

Located 80 km west of Qatar's capital, Doha, the Al Kharsaah Solar PV Independent Power Producer (IPP) project is the country's first large-scale solar...

OMV Petrom Buys 50 Pct Stake in Gabare Solar Project

OMV Petrom S.A. has acquired a 50 percent stake in the Gabare solar project from Enery Element, a large-scale project in Byala Slatina, near...

RWE 7.5MW/11MWh battery energy storage start commercial operation in Netherlands

Power generation firm RWE has put a BESS in the Netherlands into commercial operation, its first that is capable of providing inertia to the...

Gurīn Energy selects Saft’s battery energy storage system for first Japanese project

Saft, a subsidiary of TotalEnergies, has been selected by leading Asian renewable energy developer Gurīn Energy to supply a battery energy storage system (BESS)...