Serbia’s EPS to install 97.2 MW solar power plant in Kostolac

Serbia’s state-owned power utility Elektroprivreda Srbije (EPS) plans to install 97.2 MW solar power plant Srednje Kostolačko Ostrvo. The investment is estimated at EUR 84 million.

After launching the construction of the 66 MW Kostolac wind farm, this should be the company’s second major renewable energy project.

The PV plant is planned at an ash and slag dump in the Kostolac mining basin

The photovoltaic (PV) power plant should be installed at an ash and slag dump in the Kostolac mining basin, according to the answers sent by EPS to Balkan Green Energy News.

Kostolac mining basin includes open-pit coal mines and coal power plant.

The practice of installing solar power plants on the ash and slag dumps is increasingly being implemented worldwide amid phasing out coal in energy production.

EPS has earlier launched the 9.95 MW Petka solar power plant project at the Ćirikovac mine landfill, also in the Kostolac mining basin. The expected power production is 12.9 GWh per year.

EPS said that at the end of August 2019 it received the permit for its construction.

The planned capacity is 97.2 MW and the expected annual production 115 GWh

EPS anticipates the project parameters could be better because solar power cost is rapidly decreasing. Efficiency has risen by about 10% and prices dipped 20%-25%, so the cost is about EUR 8 million, down from EUR 11 million estimated in 2016.

The Srednje Kostlačko Ostrvo PV plant is the second project under development, worth EUR 84 million, with an installed capacity of 97.2 MW and an average annual production of 115 GWh, EPS said.

The project should be implemented in three years

The location for the plant is an active landfill of ash and slag from coal power plants.

Its closure and remediation must be finished before the construction, EPS said. It added the project is scheduled to be implemented in three years, with investments of about EUR 15 million.

The location spans 270 hectares and could be separated into three investment zones, allowing construction in phases.

North Macedonia’s power company ESM also decided to build solar power plants at closed mining sites and landfills of ash and slag. It has already selected one partner and is looking for another for the projects at the Oslomej lignite mine.

Brana Lazići solar power plant installed in 2016

EPS already has one smaller solar power plant. 330 kW Brana Lazići is in Zaovine, within the Bajina Bašta hydropower plant.

In 2016, the first 110 kW was installed and the remaining 220 kW in 2017.

The PV system has more than 1,000 panels. In 2018 it produced 375.9 MWh, and in the first nine months in 2019 the output reached 320.8 MWh.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Goldman expects global solar installations set to rise to 914 Gigawatts (Gw) in 2030

  Policymakers in some of the world’s largest economies are reducing support for solar power generation. Even so, Goldman Sachs Research expects rapid growth in...

Germany’s solar industry warns against subsidy cuts for rooftop installations

Germany’s solar industry has raised concerns over a proposal by Economy Minister Katherina Reiche to end feed-in subsidies for new small-scale rooftop photovoltaic (PV)...

141MW solar project proposal submitted to Australia’s EPBC Act

ACE Power and Osaka Gas Energy Australia have joined forces to develop the 141MWdc Forbes Solar Farm, which is proposed for central New South...

Swiss pilot surpasses solar-powered plane altitude record

The SolarStratos plane made the landmark flight from Sion airport in southwest Switzerland on Tuesday, taking advantage of warm air thermals to go beyond...