DISCOM and Load Despatch Center Must Compensate for Curtailment of Solar Power: APTEL

The Tribunal directed TANGEDCO and TNSLDC to compensate the developers for curtailment of power jointly

Source:MERCOM

The Appellate Tribunal for Electricity (APTEL), in a recent order, ruled that the Tamil Nadu Generation and Distribution Corporation (TANGEDCO) and the Tamil Nadu State Load Despatch Center (TNSLDC) should compensate solar developers for curtailment of power from March 1, 2017, to June 30, 2017, at 75% of the tariff listed in the power purchase agreement (PPA) along with 9% interest.
APTEL directed the TNSLDC and TANGEDCO to pay the compensation jointly within 60 days from the date of the order.
Also, the Tribunal directed the Power System Operation Corporation (POSOCO) to carry out a detailed verification of the data for the period up to October 31, 2020. POSOCO is asked to find out whether there was an intentional curtailment of power for collateral reasons by the distribution company and SLDC or whether it was on account of grid safety and submit the report to the Commission within three months.
The Tribunal also pronounced that the directions be issued to all the state electricity regulatory commissions, distribution companies (DISCOMs), and SLDCs.
The Tribunal added that as a deterrent, the curtailment of renewable energy for reasons other than grid security should be compensated at PPA tariff in the future.
The National Solar Energy Federation of India (NSEFI) had filed a petition before APTEL, challenging the validity of the State Commission’s earlier order dated March 25, 2019, regarding the curtailment of power by the DISCOMs in Tamil Nadu.
Background
In 2012, the Government of Tamil Nadu announced the Tamil Nadu Solar Energy Policy 2012, and developers willing to set up solar projects in the state were promised various incentives. Based on this, several developers set up solar projects in the state.
After the commissioning of the projects, TANGEDCO and the TNSLDC issued several instructions to solar developers citing grid security as the reason for the curtailment of power.
Aggrieved by the constant curtailment of power, the developers filed a petition with the state Commission, seeking directions to the respondents to observe the ‘must-run status’ of the solar projects and payment for the deemed generation charges for the capacity that could not be generated and supplied due to the backing down instructions issued by the respondents.
NSEFI, in its submission, said that TANGEDCO had issued orders asking the solar projects to cease generation for as much as 7-10 hours a day. This included the peak generation period out of the 12 hours of generation in the day from March 1, 2017, to June 30, 2017.
The federation added that the independent report submitted by POSOCO concluded that there was no abnormal voltage condition at the 400 kV level of the grid and no network loading issue, which required backing down or curtailment during the said period. There were no constraints that necessitated the state-wide curtailment.
The state agencies argued that the SLDC was authorized to issue backing down instructions to secure the economic operation of the grid. Also, the renewable generators were asked to back down power as the last resort after conventional power and hydropower.
After a detailed analysis, POSOCO reported that considering the grid frequency, only 5.26% (60 out of 1,140 blocks) appeared to be justified from a grid security perspective.
The state utilities said that there was no concrete proof brought on record by the NSEFI before the Commission to substantiate the allegations that backing down of power was arbitrary.
Tribunal’s analysis
The Tribunal directed the state Commission to calculate the financial loss based on the loss of generation reported by POSOCO. Such compensation must be paid whenever there is a wrongful curtailment of solar power.
TANGEDCO and TNSLDC must pay the deemed generation charges at the tariff listed in the PPA for the solar power curtailed from March 1, 2017, to June 30, 2017, for the entire backed down energy excluding 5.26% as per the POSOCO report.
The consequence of failing to comply with the statutory mandate and back down generation in the absence of any grid security or safety concerns was the payment of monetary compensation for the loss of generation.
The Tribunal stated that the state utilities had also contended that there was no concrete proof brought on record by the petitioner before the Commission to substantiate its allegation that the backing down instruction was issued arbitrarily.
The Tribunal said that the SLDC conspiring with TANGEDCO, had issued back down instructions to renewable generators for other than grid security reasons and in violation of the provisions of the Grid Code. So, the deemed generation charges must be paid by TANGEDCO.
The Tribunal further added that the investments made in establishing solar projects were premised on the ‘must-run’ status detailed in the regulations framed under the Act and the energy purchase agreement provisions.
The State Load Dispatch Centre is directed to submit a monthly report to the State Commission with detailed reasons for any backing down instructions issued to solar projects.
After considering all the facts, the Tribunal directed TANGEDCO to pay compensation for 1,080 blocks considered by POSOCO, during which curtailment instructions were issued for reasons other than grid security, at the rate of 75% of PPA tariff/kWh within 60 days from the date of this order. The respondents should pay the compensation along with interest at 9% for the entire period.
It also directed POSOCO to carry out a similar investigation up to October 31, 2020, and submit the report to the Commission within three months.
Also, the Tribunal added that as a deterrent, the curtailment of renewable energy for reasons other than grid security should be compensated at PPA tariff in the future.
APTEL has asked for a copy of the Order along with the POSOCO report to be circulated to all the State Electricity Regulatory Commissions, Ministry of New and Renewable Energy, and Ministry of Power to ensure the tribunal’s orders are complied with.
Speaking on the judgment, NSEFI CEO Subrahmanyam Pulipaka said, “This landmark judgment by Hon’ble APTEL will go a long way in reinstating confidence in the entire renewable energy sector and hold utilities and SLDCs accountable for curtailment.”
In September last year, APTEL declined a wind power generator’s appeal against the Andhra Pradesh State Load Despatch Centre and the Transmission Corporation of Andhra Pradesh, asking them to revise power curtailment instructions for wind projects connected to a substation in the state.
Earlier, NSEFI had written to the Government of Telangana, asking it to address the issue of the SLDC arbitrarily restricting solar power generation in the state.
Subscribe to Mercom’s real-time Regulatory Updates to ensure you don’t miss any critical updates from the renewable industry.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

28.29%! LONGi’s crystalline silicon cell efficiency breaks world record again

9月24日(当地时间),隆基绿色能源在欧洲正式发布了一项重大技术突破:其自主研发的高低温复合钝化背接触(HIBC)电池的光电转换效率达到28.29%,并已获得德国哈默尔恩太阳能研究所(ISFH)的认证。 这是隆基今年第三次打破晶体硅电池效率的世界纪录,此前已分别达到28.04%、28.13%和28.29%。最新的效率数据接近理论极限,达到最大值的96.2%。HIBC 电池的问世是隆基“广涉、聚焦”研发战略的里程碑式成果。通过整合多种主流电池技术的优势,公司实现了涵盖电池结构设计、核心材料制备、生产工艺和理论效率建模等各个环节的全面系统创新。此次成功有力地展现了隆基对高效电池领域的坚定承诺、自主创新能力以及核心技术的精湛掌握。 与电池一同亮相的还有采用HIBC电池技术打造的功率超过700W的组件,标志着这项前沿技术成功实现量产。这也凸显了隆基在高端光伏产品制造和先进技术商业化方面的强大实力。 在全球能源转型的大背景下,隆基绿色能源始终致力于构建完整的清洁能源价值链,力求提供融合绿色电力、绿色氢能和储能的一体化解决方案。展望未来,隆基将继续坚持自主创新,通过技术革新推动行业发展。公司致力于为全球市场提供高品质、多功能的光伏产品,积极支持全球能源转型,并携手构建以零碳排放和可持续发展为特征的绿色能源新格局。

Croatia’s Zito launches 3.9 mln euro PV power plant

克罗地亚食品生产商Zito周三宣布,已在位于克罗地亚东部切平(Cepin)的食用油工厂建成一座耗资385万欧元(约合440万美元)的太阳能光伏电站,装机容量为3.5兆瓦时(MWh)。这是该公司在该工厂建设的第二座光伏电站。Zito 在一份新闻稿中表示,该电站还配备了一套功率输出为4.5兆瓦、容量为9兆瓦时的储能系统。 该项目由欧盟支持的复苏与韧性计划共同出资,旨在帮助企业向节能高效型经济转型。 该电站于8月下旬投入试运行。其预计年发电量为5500兆瓦时,而工厂的总用电量超过10130兆瓦时。所发电量将用于满足工厂自身用电需求,剩余电力将存储在储能系统中。 “我们投资新建了一座太阳能发电厂,以补充现有的发电厂,该发电厂已于2023年投入运营。这座新电厂规模更大,两座电厂合计将满足切平油厂超过60%的总用电量,”该厂首席执行官卡洛·杜达斯表示。 这项对新太阳能发电厂的投资是在公司去年首次公开募股(IPO)期间宣布的,当时该公司在萨格勒布证券交易所筹集了1.3亿欧元。 周三,Zito(股票代码:ZITO)股价上涨1.14%,收于17.80欧元。 (1美元=0.867欧元)

Enexus, LONGi to deploy 50 MWh of BESS across two projects in Romania

Romanian renewables developer Enexus will deploy 50 MWh of battery energy storage system (BESS) capacity in the southern town of Titu, Dambovita county, using...

Solar panel catches fire on roof of industrial building near Okolona

A large industrial facility in south Louisville caught fire on Wednesday. The fire was reported just before 3 p.m. Wednesday in the 8700 block of...