星期五, 20 6 月, 2025
Home PV News North America Speed up interconnection studies with enforceable timelines and third-party competition, say SEIA...

Speed up interconnection studies with enforceable timelines and third-party competition, say SEIA and allies

The proposed measures would prompt transmission providers to complete studies on time, the groups said. They asked federal energy regulators for an accelerated interconnection rulemaking.

Source:pv magazine

The clean energy industry has presented a plan to accelerate interconnection studies through efficiency, timelines, and competition, in comments to the Federal Energy Regulatory Commission (FERC).

So that interconnection studies for large-scale renewables projects may be completed in “months instead of years,” three clean energy trade groups have asked FERC to launch an “accelerated, stand-alone” interconnection rulemaking to implement their recommended approach.

The groups are the solar association SEIA, clean energy trade group Advanced Energy Economy, and renewables and transmission trade group American Clean Power Association.

The plan would provide interconnection customers the option of using third-party consultants to produce required studies.To enable both transmission providers and third parties to produce such studies efficiently, the plan calls for creation of standardized unit pricing and criteria for planning and construction, especially for facilities studies. Those studies can now take over two years to complete, the groups say.

The plan would also require transmission providers to meet minimum standards for interconnection study timeliness and accuracy, with “enforceable, non-recoverable financial penalties for underperformance.”

The groups say that timelines and penalties, together with third-party competition, “will incentivize transmission providers and owners to devote sufficient resources and staffing to completing accurate studies on time.”

Among 21 near-term and long-term solutions, the groups also recommend:

Clear guidance for converting, during the study process, stand-alone resources to hybrid or co-located resources (e.g., by adding storage),
Requiring transmission providers, upon receiving an interconnection request, to evaluate grid-enhancing technologies that could substitute for added transmission capacity, and
Making interconnection customers responsible only for network upgrades “local” to their project.
The groups asked FERC to require all transmission providers to use practices comparable to those of transmission providers that have “already implemented” the reforms identified in their comments.

Of FERC’s five commissioners, currently three are Democrats and two are Republicans.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

RWE 7.5MW/11MWh battery energy storage start commercial operation in Netherlands

Power generation firm RWE has put a BESS in the Netherlands into commercial operation, its first that is capable of providing inertia to the...

Gurīn Energy selects Saft’s battery energy storage system for first Japanese project

Saft, a subsidiary of TotalEnergies, has been selected by leading Asian renewable energy developer Gurīn Energy to supply a battery energy storage system (BESS)...

Swiss 1.6 GWh redox flow storage project starts to build

Flexbase Group has begun construction on what could become one of Europe’s largest flow battery storage installations, breaking ground on an 800 MW/1.6 GWh...

Analysis: UK’s solar power surges 42% after sunniest spring on record

The UK’s solar farms and rooftops generated more electricity than ever before in the first five months of 2025, as the country enjoyed its...