Home PV News SPDA seeks more time from govt for commissioning solar projects amid pandemic

SPDA seeks more time from govt for commissioning solar projects amid pandemic

The association has highlighted the continued challenges that the solar power industry is facing for the last year.

Source:Energyword

The Developers Association (SPDA) has urged the Ministry of New and Renewable Energy (MNRE) to give three more months for commissioning solar projects amid the the raging pandemic. The association has highlighted the continued challenges that the solar power industry is facing for the last year.
It has requested MNRE for a blanket extension of an additional three months in SCoD (scheduled date of commissioning) of solar power projects in addition to five months granted by MNRE earlier, an SPDA statement said.
The government had taken the problems into cognizance and provided relief in blanket extension for five months through an office memorandum on August 13, 2020.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Al Kharsaah: A Pioneering Solar Power Plant in Qatar

Located 80 km west of Qatar's capital, Doha, the Al Kharsaah Solar PV Independent Power Producer (IPP) project is the country's first large-scale solar...

OMV Petrom Buys 50 Pct Stake in Gabare Solar Project

OMV Petrom S.A. has acquired a 50 percent stake in the Gabare solar project from Enery Element, a large-scale project in Byala Slatina, near...

RWE 7.5MW/11MWh battery energy storage start commercial operation in Netherlands

Power generation firm RWE has put a BESS in the Netherlands into commercial operation, its first that is capable of providing inertia to the...

Gurīn Energy selects Saft’s battery energy storage system for first Japanese project

Saft, a subsidiary of TotalEnergies, has been selected by leading Asian renewable energy developer Gurīn Energy to supply a battery energy storage system (BESS)...