The 500-MW Nunez de Balboa solar photovoltaic (PV) park in the Spanish region of Extremadura fed its first megawatt-hour to the grid at noon today, its owner Iberdrola SA (BME:IBE) has announced.

The mega-project, promoted by Iberdrola and local operation and maintenance (O&M) specialist Grupo EcoEnergias del Guadiana SA, required an investment of nearly EUR 300 million (USD 324.1m) to build. The solar complex is located between the municipalities of Usagre, Hinojosa del Valle and Bienvenida in Badajoz province.

The facility needed 1.43 million solar panels, 115 inverters and two substations, while more than 1,200 workers were present at the site at peak construction times, the Spanish utility said.

Nunez de Balboa operates under long-term power purchase agreements (PPAs) with Spanish lender Kutxabank SA, telecommunications company Euskaltel SA and food distributor and supermarket operator Uvesco SA. Its annual output can satisfy the electricity needs of 250,000 people per year.

Iberdrola has more than 1,300 MW of PV projects lined up for construction in Extreamadura by 2022. The company has submitted paperwork for six projects – the 590-MW Francisco Pizarro, the 328-MW Ceclavin, 150-MW Arenales, the 50-MW Majada Alata, the 50-MW San Antonio and the Campo Aranuelo I, II and III of 150 MW in total.

The construction of Campo Aranuelo, which will also feature battery storage, is expected to start shortly, Iberdrola said.

On top of these, the company has grid-access rights to connect 300 MW, which is enough to fit one more PV project, it said.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Six American Cities Excelling in Renewable Energy Use

As Americans across the country celebrate Earth Day, begun by Gaylord Nelson and Denis Hayes in 1970, six cities have been singled out as...

Alcemi Secures Planning Permission for 300 MW BESS Project

Alcemi, an energy storage developer,has received planning permission for their 300 MW Kintore BESS in Aberdeenshire, Scotland. The Kintore BESS is located on a brownfield...

Second phase of 490 MW PV plant in Peloponnese coal land starts to build

Terna won the contract for the construction of the second of the three parts of a 490 MW solar park in Megalopolis, on former...

Romania launches renewables auction for 3.5 GW

Following a successful first round, in which developers won government support for projects of 1.53 GW altogether, the Romanian Ministry of Energy issued another...