Vestas says a loose connection in the electrical system started the fire in the V112 3 MW wind turbine at the Gross Eilstorf wind farm in Germany on 30 March.

The fire started in the harmonic filter cabinet due to a loose connection in the electrical system, which created an arc flash.

Vestas says the issue is being addressed by using a different type of washer on the the electrical connections in the wind turbine's harmonic filter cabinet.

V112 customers have been informed, and Vestas is already in the process of replacing washers at the same time as performing other planned upgrades and maintenance of the wind turbines.

The burnt nacelle has already been replaced, and is scheduled to be re-commissioned this week.

Vestas still is awaiting the reports from two external experts who worked side-by-side with Vestas investigators. The these reports are expected within a few weeks, and Vestas says it is confident that this final conclusion will be confirmed.

LEAVE A REPLY

Please enter your comment!
Please enter your name here

- Advertisment -

Most Popular

Al Kharsaah: A Pioneering Solar Power Plant in Qatar

Located 80 km west of Qatar's capital, Doha, the Al Kharsaah Solar PV Independent Power Producer (IPP) project is the country's first large-scale solar...

OMV Petrom Buys 50 Pct Stake in Gabare Solar Project

OMV Petrom S.A. has acquired a 50 percent stake in the Gabare solar project from Enery Element, a large-scale project in Byala Slatina, near...

RWE 7.5MW/11MWh battery energy storage start commercial operation in Netherlands

Power generation firm RWE has put a BESS in the Netherlands into commercial operation, its first that is capable of providing inertia to the...

Gurīn Energy selects Saft’s battery energy storage system for first Japanese project

Saft, a subsidiary of TotalEnergies, has been selected by leading Asian renewable energy developer Gurīn Energy to supply a battery energy storage system (BESS)...