Environmental regulators in Chile’s Antofagasta region have approved two solar projects worth a combined USD 688 million, the Environmental Evaluation Commission (Coeva) confirmed on 30 October.
SQM won unanimous approval for a USD 111 million scheme at its Coya Sur site: a 76 MWp photovoltaic plant, a 320 MWh battery energy storage system and a 7-kilometre, 66 kV line to an existing substation. The mining company filed its environmental impact declaration in December 2025, and the Environmental Evaluation Service said the review took 304 days, 24% faster than the 2025 average for such filings.
The same session cleared Spanish developer Grenergy’s Elena 2 park in the Maria Elena commune, a USD 577 million project with 566 MWp of capacity built from 906,000 panels of 625 Wp each, plus battery storage tied to Chile’s National Electric System. Elena 2 finished review in 268 days, 33% below the 2025 average.
Faster permitting matters in a market where midday solar output increasingly needs storage behind it. Both approvals point to continued momentum for hybrid solar-plus-storage in the country’s mining-heavy north.